Kakata–Bong Mines Road Aggregate Supply

WellDone Group supplied graded base course, sub-base and 3/4" chippings across a twelve-month programme supporting the rehabilitation of 46 km of trunk road between Kakata and the Bong Mines corridor.

Production was scheduled against the contractor's laying programme, with each consignment released only after grading verification. Despite two extended rain periods, monthly delivery targets were met in eleven of twelve months.

Scope of work

  • Quarry production scheduling against the laying programme
  • Crushing and screening to specified gradings
  • Per-consignment grading verification and test certification
  • Haulage to seventeen stockpile points along the corridor

Project details

Status
Completed
Division
WellDone Mining Services
Client
Liberia National Road Authority
Location
Margibi & Bong Counties
Duration
Feb 2024 – Jan 2025

Key facts

Material supplied
180,000 m³
Corridor length
46 km
Stockpile points
17
Programme
12 months

Have a similar requirement?

We would be glad to discuss scope, timing and cost.

Request a Quote
More work

Related projects

Concession Site Quarry Development
Completed WellDone Mining Services

Concession Site Quarry Development

Grand Cape Mount County Apr 2023 – May 2024

Development and operation of a captive quarry supplying haul-road and platform material to a mining concession.

Stay informed

Project updates, tenders and company news — a few times a month, no more.